WHAT HAPPENS BEFORE AND AFTER INSTALLATION

The solar installation and legalisation process in Andalucía

The roof work may be brief. Design, electrical documentation, regional registration and supplier processing are separate parts of a completed solar project.

Reviewed August 2026

QUICK ANSWER

What are the main stages of installing solar panels in Andalucía?

A typical project moves through consumption review, roof survey, technical design, any property or municipal checks, installation, electrical certification, Andalucía registration and supplier processing for surplus compensation where applicable.

Survey the property before fixing the design

The survey checks roof form, condition, orientation and shade along with safe access and equipment positions. Electricity bills show the scale and timing of demand. The designer also needs to know about pool pumps, cooling, hot water and future electrical loads.

The result should be a defined panel layout, inverter architecture, predicted production and installation scope. A battery or backup arrangement needs its own load priorities.

Resolve ownership and permissions early

Detached homes, apartment communities, protected buildings and commercial premises do not present the same administrative position. Roof rights, community approval and local requirements should be identified before equipment is ordered.

For collective self-consumption, the participating supplies and allocation agreement create additional work. The IDAE publishes a dedicated guide for collective arrangements and communities of owners.

Certification and regional registration are part of completion

The Junta de Andalucía explains that legalisation begins with the identifying CAU code from the electricity distributor, followed by the applicable regional procedure. The electrical installation also requires the relevant technical documentation and certification.

A finished array on the roof is not the same as a completed administrative process. The proposal should name the party responsible for each stage and the documents the owner will receive.

Surplus compensation follows the registered system

Where the installation is eligible and the owner chooses simplified compensation, unused generation is exported and its value is applied under the electricity supply contract. IDAE explains that the valuation depends on whether the customer is on the regulated or free market.

Supplier processing can continue after the physical installation. Ask for the timetable to distinguish the installation date, legalisation and the point at which export compensation is expected to appear on bills.

PEOPLE ALSO ASK

Questions linked to this decision

What is a CAU code for solar in Andalucía?+

It is the code that uniquely identifies the self-consumption installation. The Junta de Andalucía identifies obtaining it from the electricity distributor as an early legalisation step.

Who registers a solar installation in Andalucía?+

The proposal should state who prepares and submits the required technical documentation. Do not assume registration is included unless it appears in the scope.

Can solar panels be installed on an apartment community?+

Potentially. Roof ownership, community decisions, participating supply points and the chosen collective self-consumption arrangement must be resolved.

When does surplus compensation start?+

It depends on completed registration and processing by the relevant distributor and electricity supplier. It may not begin on the day the panels are installed.

Do all solar systems require the same paperwork?+

No. Power, connection arrangement, property type, export status and whether the system is individual or collective can affect the procedure.